Execution

Issues and change requests

The requester creates the change with its reason and options, the system calculates its impact on milestones, budget, dependencies, and indicators, the owners review it, and the authority holder approves it according to value thresholds, issuing a new version of the baseline while the previous one is kept unchanged. PMO-UC-04 PMO-DATA-003/007 ENT-PMO-033

IssueProjectSeverityOwnerDateStatus
Authority holderCostTimeScopeBenefit
Project manager≤ 0.2 M from the reserve≤ week without impacting a milestoneClarification only—
Executive sponsor≤ 1.0 m≤ 4 weeksWithin the target± 5%
Portfolio committee> 1.0 m> 4 weeksChanges the objectiveAny larger reduction
Configured in Setup · ENT-PMO-002